System Maintenance: Today Saturday, November 23, 2024, from 11:00PM to Sunday, November 24 at 7:00AM, our EZ Pay credit card payment processing may not be available; however, you may make a payment by logging in to Manage My Account. You may report an outage online or by calling (210) 353-4357. Visibility to bills in Manage My Account may also not be available during this maintenance.
Blanco & W. Bitters
COMMITMENT TO RELIABLE SERVICE
As part of our ongoing commitment to deliver reliable gas and electric service, we routinely evaluate our systems and perform maintenance as needed. It is our goal to inform customers near construction zones prior to beginning any work and maintain up-to-date information on our website.
SCOPE OF PROJECT
In early 2017, a non-CPS Energy contractor installing telecommunications fiber damaged a twelve-inch natural gas line at the southwest corner of the Blanco Road and Bitters Road intersection. Our crews identified the location of the damage, ensured the site was safe, and made interim repairs. Permanent repairs needed to be made.
During hours of active construction (7pm – 5am, Sunday through Thursday), two southbound lanes of Blanco Road must be shut down south of the Blanco/Bitters intersection along with two eastbound lanes of Bitters Road west of the intersection. The left turn lane of Bitters Road east of the intersection must also be shut down during hours of active construction. The lane closures shall be reduced to one closed southbound lane of Blanco Road and one closed eastbound lane of Bitters Road while our crews are not actively working at the site.
ESTIMATED TIMELINE
The project is expected to begin as early as Monday, April 24, 2017 and to be completed by Friday, May 5, 2017.
PROJECT UPDATES
05/05/2017: Project completed
PROJECT CONTACT
For more information, please contact our Customer Response Unit at 210.353.CRU3 (2783).