System Maintenance: On Sunday, March 15, 2026, from 1:00 AM to 5:00 AM, our EZ Pay with credit card payment processing may be unavailable. However, you can still make a payment by logging in to your "Manage My Account" account. You may report an outage online or by calling (210) 353-4357. Visibility to bills in Manage My Account may also not be available during this maintenance.
Inwood/Deerfield Neighborhoods
COMMITMENT TO RELIABLE SERVICE
In an effort to continuously improve the delivery and reliability of electric service to our community, we are performing a multi-phase project to help mitigate the risk of power outages in northwest San Antonio.
SCOPE OF PROJECT
The work consists of extensive tree trimming in contact with overhead lines and installing animal guards at our nearby substation. As phases of our work are completed, area residents can expect to see an improvement to the reliability of their electric service.
ESTIMATED TIMELINE
This project is expected to begin January 2018 and be completed by March 2018.
PROJECT UPDATES
01/02/2018: Reliability concerns investigated
01/04/2018: HOA meeting
01/26/2018: Project completion dates established
03/05/2018: Project completed
PROJECT CONTACT
For more information, please contact us at 210.353.2222